Lagos blue rail line nears completion, as engineers launch final track beam

Published

on

Blue line

The race to the completion of the 27-kilometre Lagos Blue Line Rail Mass Transit has begun, with the launch of the last track beam (T-beam) of the rail track on Wednesday.

Governor Babajide Sanwo-Olu witnessed the historic moment and personally flagged off the engineering procedure held at the site of the iconic Marina station of the rail project.

With the laying of the final T-Beam, all difficult civil works standing in the way of the Lagos Blue Rail Line, which started in 2012, have been overcome. The contractor – China Civil Engineering Construction Corporation (CCECC) – will now go ahead to set the rail tracks along the alignment and move the project to completion.

Sanwo-Olu, again, committed the Lagos Metropolitan Area Transport Authority (LAMATA) and the contractor to the December deadline for the Blue Line project’s completion.

Lagos Government will be delivering two rail mass transit projects within the first term of the Sanwo-Olu administration. The Blue Line, which traverses between Mile 2 and Marina, will be operated on Electric Motor Unit (EMU); the 37-kilometre Red Line, from Agbado to Ebute Metta, will operate on Automotive Gas Oil (AGO).

Speaking at the launch of the last T-Beam on the Blue Line, Sanwo-Olu said the achievement signposted his administration’s commitment to bringing succor to Lagosians and give them choices in mass transportation.

The Governor said the rail projects represented the audacity of his administration’s vision to deliver a robust integrated transit system as encapsulated in the Traffic Management and Transportation pillar of his Government’s T.H.E.M.E.S. development agenda.

He said: “Today’s final T-beam launch indicates that we are gradually inching to the completion of the civil infrastructure for the first phase of the Blue Line traversing from Mile 2 to Marina.

“The engineering work today completes a total of 1,967 piles foundation, while we have also completed three 306 platforms, 310 piers, 267 cover beams and erection of 984 T-beams.

“We are not just making promises; people are beginning to see for themselves that all the milestones and the difficult tasks we are meant to achieve to ensure operation of the Blue Line are being achieved.

The Marina Station, which is the iconic terminal for the Blue Line, will be completed within two-and-half months. I am restating here that we will formally complete this Blue Line before December 31, 2022.”

The Governor said the two sets of EMU coaches already procured for the Blue Line operations would arrive in Lagos from China before the end of October. He said the rail line would be test run immediately after completion, while passenger movement would start within the first quarter of 2023.

Sanwo-Olu said the construction of the second phase of the Blue Line project would commence after the start of operation, which would extend the rail project from Mile 2 to Okokomaiko.

He said Blue Line stations would be built at Festac, Alakija, Trade Fair, Volkswagen, LASU and Okokomaiko. The Governor disclosed that talks were being held with the Ogun State Government for possible extension of the rail line to Agbara.

He said: “The second phase of the Blue Line project will be an easy infrastructure to develop because the marked alignment for stations and tracks are largely at grid level.

“While we are at this, the Red Line is also on the way. This is a start-and-end project for our administration, with about seven stations concurrently being built. This will redefine mass transportation in Lagos.

“To our citizens, I say the Blue Line is for real and you will ride on it in no distant future. For the Doubting Thomases and people that do not like our face, their eyes cannot disbelieve in the infrastructure we are bequeathing to the citizens of our State.

“They cannot disbelieve in our bold effort and commitment to improve mobility and deliver transport infrastructure that brings ease to our people.”

LAMATA Managing Director, Engr. Abimbola Akinajo, said the first 13-kilometre stretch of the Blue Line construction was divided into four phases to enable the government fund the project from its internally generated revenue.

To get to the current status, she said the construction work experienced disturbances and delays in the relocation of submarine cables, submarine natural gas pipelines, and removal of underground shipwrecks.

“Just as we are laying the final T-beam for the rail tracks, we are also currently retrofitting the train stations at Mile 2, Alaba, Iganmu and National Theatre with light in readiness for passenger operation in the first quarter of 2023,” Akinajo said.

CCECC chairman, Mr. Liu Wei Min, described the event as the most significant level of the project.

He said: “We express our sincere gratitude to the present administration under the leadership of Mr. Sanwo-Olu in reaching this milestone. We will continue to work to meet the ultimate target in delivering the entire project with high standards and quality.”

The T-beam laying event was also attended by Consul General of the People’s Republic of China in Lagos, Mr Chu Mao ming.

Author

Add your voice

0 comments

People reading currently

FuturizeU supports development of innovative healthcare products in Africa FuturizeU supports development of innovative healthcare products in Africa
Social Entreprenuership3 weeks ago

FuturizeU supports development of innovative healthcare products in Africa

Futurize and AstraZeneca are investing in social entrepreneurs who are developing innovative products that are addressing healthcare equity and early...

Banjul International Airport in Gambia Banjul International Airport in Gambia
Dev. Finance3 weeks ago

Saudi Fund for Development advocates Climate Change Mitigation, Social Infrastructure Investments in Africa

  The Saudi Fund for Development (SFD) has advocated for the preservation of heritage projects in Africa through initiatives such...

Catalyst Fund Team Catalyst Fund Team
Climate & Environment3 weeks ago

Catalyst Fund Raises First Round of $40 million investment in African Climate Startups

The Catalyst Fund has achieved the initial close of its $40 million fund for investing in climate startups in Africa....

Paystack CEO, Shola Akinlade, buys majority stake in Aarhus Fremad Paystack CEO, Shola Akinlade, buys majority stake in Aarhus Fremad
Sports6 months ago

Paystack CEO, Shola Akinlade, buys majority stake in Aarhus Fremad

A Danish football club, Aarhus Fremad announced on Tuesday that it has sold  55 percent of its shares to the...

MRI is increasing survival rate of women with breast cancer- PPC MRI is increasing survival rate of women with breast cancer- PPC
Climate & Environment6 months ago

MRI is increasing survival rate of women with breast cancer- PPC

PPC Limited, Nigeria’s leading engineering and infrastructure development company with footprints across Nigeria’s healthcare landscape, says that the advancement of...

Adeleke versus Oyetola Adeleke versus Oyetola
Policy & Regulation6 months ago

Appeal court upholds Senator Ademola Adeleke’s win in Osun

The Court of Appeal Abuja has overturned the ruling of the Osun State Governorship tribunal and has declared Senator Ademola Adeleke...

Lawmaker demands revamp of bank e-payment platforms Lawmaker demands revamp of bank e-payment platforms
Dev. Finance6 months ago

Lawmaker demands revamp of bank e-payment platforms

The members of the House of Representatives have demanded that the Central Bank of Nigeria (CBN) direct banks to revamp...

CBN to destroy naira notes worth N6tn CBN to destroy naira notes worth N6tn
Economy6 months ago

We’ve disbursed N20bn to alleviate cash crunch, CBN tells NLC

The Central Bank of Nigeria (CBN) met with the leadership of the Nigeria Labour Congress (NLC) in Abuja on Thursday,...

 Apply for Amazon Accelerator programme for fintech founders  Apply for Amazon Accelerator programme for fintech founders
Opportunities6 months ago

 Apply for Amazon Accelerator programme for fintech founders

Application closes April 27, 2023 Today, Amazon Web Services’ Startup Loft Accelerator team announced the inaugural launch of its AWS...

Fully Funded Rotary Peace Fellowships for Masters students Fully Funded Rotary Peace Fellowships for Masters students
Fellowships6 months ago

Fully Funded Rotary Peace Fellowships for Masters students

Application Deadline: May 15, 2023 Each year, Rotary awards fully funded fellowships for dedicated leaders from around the world to...

Ad Blocker Detected!

Advertisements fund this website. Please disable your adblocking software or whitelist our website.
Thank You!

you're currently offline